Knowledge Base

PRJ98: SNLT Constraint When Work Assigned Before Task Start Date

Article ID: 196264

Article Last Modified on 1/23/2007


APPLIES TO


This article was previously published under Q196264

SYMPTOMS

In a project that is scheduled from Project Finish Date, if you enter a value in the timephased Work field for a task before the start date of the project, Microsoft Project assigns a Start No Later Than (SNLT) constraint to the task.

CAUSE

This behavior may occur when you assign work before the start date of the project to a task and you are scheduling the project from a finish date.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.

Keywords: kbbug kbpending KB196264