PRJ98: Task May Have Incorrect Predecessor or Successor
Article ID: 189898
Article Last Modified on 1/23/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q189898
SYMPTOMS
In Microsoft Project 98, when you change a predecessor or successor in the
Task Form view, the change may not be saved. You may also see this behavior using the Task Details Form and the Task Name Form views. You may also see that the predecessor or successor change may not be updated in the Predecessor or Successor field in the Task Table.
CAUSE
This behavior may occur when:
- You have a task that has predecessor and successor
relationships.
- You change a predecessor or successor for a task using the
Predecessor Name field or the Successor Name field in
the Task Form, Task Details Form or Task Name
Form view.
WORKAROUND
Use either of these workarounds if you have not installed SR-1.
Workaround 1
Change the
Predecessor or
Successor using the
Predecessor ID or
Successor ID column rather than the
Predecessor Name or
Successor Name column in the
Task Form view.
Workaround 2
To change the predecessor using the task name of the predecessor, follow
these steps:
- Select the task where you want to change the predecessor.
- On the Project menu, click Task Information and then
click the Predecessors tab.
- Click the cell below the Task Name column heading to select
from the list the desired Predecessor task name and click
OK.
RESOLUTION
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
STATUS
This problem was corrected in Microsoft Project 98 for Windows, ServiceRelease 1 (SR-1).
For additional information about obtaining and installing SR-1, please see
the following article in the Microsoft Knowledge Base:
185102 PRJ98: How to Obtain and Install MS Project 98 SR-1
Keywords: kbbug kbfix KB189898