PRJ98: Leveling Week by Week Gives Unnecessary Delay and Splits
Article ID: 188783
Article Last Modified on 1/23/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
This article was previously published under Q188783
SYMPTOMS
In Microsoft Project 98, when you use resource leveling, you may find
unnecessary delays and splits for linked tasks.
CAUSE
This problem occurs when you use resource leveling in Microsoft Project 98
and "Look for overallocations on a 'Week by Week' basis" is selected in the
Resource Leveling dialog box, and the task has a predecessor task.
RESOLUTION
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
After opening the project in Microsoft Project 98 SR-1, use resource
leveling on the project again. The unnecessary delay and splits will be
resolved correctly.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Keywords: kbbug kbfix KB188783