PRJ98: Elapsed Duration Lost When Opening MPX File in Project 4
Article ID: 187490
Article Last Modified on 1/23/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
This article was previously published under Q187490
SYMPTOMS
In Microsoft Project 4.0, 4.1, and 4.1a, when you open an MPX 4.0 file that was saved in Microsoft Project 98, tasks that had an elapsed duration will no longer have an elapsed duration and their duration values may change.
CAUSE
This problem occurs because Microsoft Project 98 schedules differently than
earlier versions.
WORKAROUND
To work around this problem, use either of the following methods.
Method 1: Change the Location of the Duration Field
Change the location of the Duration field in the Export table by following
these steps:
- In Microsoft Project 98, on the View menu, point to Table: <table
name> and click More Tables.
- In the More Tables dialog box click the Task option
button.
- In the list of tables, click Export, and then click
Edit.
- In the Field Name column, click Duration, and then
click Cut Row.
- In the Field Name column, click Early Start, and then
click Paste Row.
- Click OK.
- In the More Tables dialog box, click Close.
- Resave your project as MPX 4.0 format. (On the File
menu, click Save As. In the File Save dialog box, click
MPX 4.0 (*.mpx) in the Save As Type list.)
Elapsed duration tasks will now be displayed correctly when you open the
file in earlier versions of Microsoft Project.
Method 2: Change the Task Type to Fixed Duration
Change the
Task Type to
Fixed Duration by following these steps:
- In Microsoft Project 98, select the task that has an elapsed duration
value.
- On the Project menu, click Task Information and then
click the Advanced tab.
- In the Task Type list click Fixed Duration. Click
OK.
- Resave your project as MPX 4.0 format. (On the File menu,
click Save As. In the File Save dialog box, click
MPX 4.0 (*.mpx) in the Save As Type list.)
Elapsed duration tasks will now be displayed correctly when opening the
file in earlier versions of Microsoft Project.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Additional query words: PRJ98
Keywords: kbbug kbconversion kbnofix KB187490