Knowledge Base

PRJ98: Incorrect BCWP for Resource Assignment with Cost/Use

Article ID: 180922

Article Last Modified on 1/22/2007


APPLIES TO


This article was previously published under Q180922

SYMPTOMS

In Microsoft Project 98, in the Task Usage or Resource Usage view, the Budgeted Cost of Work Performed (BCWP) field for a resource assignment may contain an incorrect value. The BCWP field for the task however shows the correct value.

CAUSE

This behavior occurs when you assign a cost per use (Cost/Use) to a resource, and then assign this resource to a task that is between 0 and 100 percent complete.

Microsoft Project treats the cost per use as a prorated cost for the resource assignment. Instead, cost per use should be assigned at the beginning or end of the assignment. This only occurs when the task's percent complete is either 0 or 100 percent.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Keywords: kbbug kbpending KB180922