PRJ: Resource Units Change When Work Changed on a Summary Task
Article ID: 180632
Article Last Modified on 1/22/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
This article was previously published under Q180632
SYMPTOMS
In Microsoft Project, when you change the value of Work or Actual Work
for a summary task's resource assignment, the units for that summary task's
resource assignment are recalculated.
CAUSE
A summary task's Start and Finish dates are defined by the tasks indented
under the summary task. When you change the Work or Actual Work for a
summary task's resource assignment, the Start and Finish dates for the
summary task can not change; therefore, Microsoft Project recalculates the
Units of the resource.
Additional query words: prj2000
Keywords: kbbug kbnofix KB180632