PRJ: Unexpected Value in Actual Overtime Cost and Overtime Cost
Article ID: 178700
Article Last Modified on 1/22/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
This article was previously published under Q178700
SYMPTOMS
In Microsoft Project, you may find that the Overtime Cost and Actual
Overtime Cost fields equal zero when they should contain a cost. In
addition, you may find that the Cost for a task does not include Overtime
Cost when it should.
For example, if a resource that is assigned an Overtime Rate is assigned to
a task, when the task is set to 100% complete, the Overtime Rate is not
included in the Cost, Overtime Cost, or Actual Overtime Cost field.
CAUSE
This behavior occurs when the option Actual Costs Are Always Calculated by
Microsoft Project is turned off and the task is set to 100% complete or
when Actual Overtime Work is entered for a task.
WORKAROUND
The only way to avoid this behavior is to turn on the option Actual Costs Are Always Calculated by Microsoft Project, remove the Actual Overtime Cost, and then reassign the Actual Overtime Cost to the task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Additional query words: prj2000
Keywords: kbbug kbpending KB178700