Start and Finish dates for a task are different from assignment Start and Finish dates in Project
Article ID: 178187
Article Last Modified on 1/22/2007
APPLIES TO
- Microsoft Project 2002 Professional Edition
- Microsoft Project 2002 Standard Edition
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
This article was previously published under Q178187
SYMPTOMS
In Microsoft Project, a task's Start and Finish dates may be different
than the Resource Assignment's Start and Finish dates for the resource
assigned to that task.
CAUSE
This behavior occurs when the resource assigned to a task uses a calendar
with different working times than the Project Calendar, and the task type
is Fixed Duration. The task is scheduled by the Project calendar, and the
Resource Assignment is scheduled by the Resource Calendar.
WORKAROUND
To work around this problem, change the Task Type to Fixed Units or Fixed
Work by following these steps:
- Using the right mouse button, right-click the task and then click
Task Information on the shortcut menu.
- Click the Advanced tab.
- In the Task Type list, click to select Fixed Units, or
Fixed Work, and then click OK.
STATUS
Microsoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.
MORE INFORMATION
For example, assign a task with a resource using the 24 Hours Calendar to
start at 5:00 PM on Friday and finish at 1:00 AM on Saturday. If you change
the Task Type to Fixed Duration, the task's Start time becomes 8:00 AM on Monday and the Finish time becomes 5:00 PM on Monday. The resource assignment's Start time remains 5:00 PM on Friday and the Finish time remains at 1:00 AM Saturday as expected.
NOTE: Similar behavior can also occur when a resources Work contour is modified, such as when a Delay or Leveling Delay is assigned to the Resource Assignment.
Additional query words: PRJ2002 prj2000
Keywords: kbbug kbpending KB178187