PRJ: Complete Indicator Missing from 100% Completed Task
Article ID: 170716
Article Last Modified on 1/20/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
This article was previously published under Q170716
SYMPTOMS
A task that is set to 100% complete does not show the complete indicator
next to the task.
CAUSE
This behavior occurs when you set a task to 100% complete and then change
the Actual Finish date to NA. Although the task remains 100% complete, the
complete indicator will be removed.
WORKAROUND
To work around this problem, and show the complete indicator for the task,
do either of the following:
- Re-enter the task as being 100% complete.
-or-
- Enter an Actual Finish date for the task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Additional query words: prj2000
Keywords: kbprb kbusage KB170716