Article ID: 169597
Article Last Modified on 1/19/2007
Work = Total Work * (Resource Units/Total Resource Units)For example, if you have a 2-day (2d) duration task where a resource (R1) is assigned 200%, the 2d duration task calculates to 32 hours (32h) of work. If you add a new resource (R2) to the task, then Microsoft Project calculates work and duration for each resource in the following manner:
21.33h = 32h Total Work * (200% R1 Units/300% Total Units)Resource R2 Work:
10.67 = 32h Total Work * (100% R2 Units/300% Total Units)
NOTE: Total Units (300%) is calculated by adding the R1 resource unit (200%) and the R2 resource unit (100%).
2.67d = 21.33h (R1 Total Work)/100% (R1 Units based on 8 hour day) 1.33d = 10.67h (R2 Total Work)/100% (R2 Units based on 8 hour day)The duration of the task changes from 2d to 2.67d due to the length of time necessary for the driving resource to complete it's assigned work. The driving resource for a task is determined to be the highest ratio of Work/Units for all resource assignments on a task. In this example, R1 is the driving resource because 2.67d is higher than 1.33d. Based on an 8-hour day, it will take R1 2.67d to complete 21.33h of work.
Additional query words: 98 mulitple edit work
Keywords: kbinfo kbother KB169597