PRJ: Can't Select Some Options After Global Resource Time Change
Article ID: 163822
Article Last Modified on 1/19/2007
APPLIES TO
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
This article was previously published under Q163822
SYMPTOMS
When you make a global change to a resource calendar to change all of the
working times for the month to something other than the default times, you
cannot select the Nonworking or Default options in the Change Working Time dialog box for a single day.
WORKAROUND
To work around this problem, use the following steps:
- On the Tools menu, click Change Working Time.
- From the For box, select the resource you want to
modify.
- On the calendar, select the day you want to change.
- Under Working Time, delete the From and To
settings.
- Reselect the Calendar day by clicking on it, then click the
nonworking or default options.
You can now click to select the Nonworking or the Default options under
Make Date(s).
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
MORE INFORMATION
Additional query words: kbusage kbhowto
Keywords: kbbug kbpending KB163822