PRJ: Project Lag Uses Base Calendar Instead of Resource Calendar
Article ID: 159773
Article Last Modified on 1/19/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q159773
SYMPTOMS
When you specify lag time to delay a task, the task may appear to be
incorrectly scheduled.
This behavior may occur when a resource assigned to a task has a different
calendar than the base calendar. At this point, the portion of the task
where the lag is scheduled is scheduled using the Base Calendar.
Microsoft Project uses the Base Calendar to schedule lag to avoid any
potential conflicts when scheduling multiple resources.
Additional query words: prj2000 4.10a lead lag
Keywords: kbbug KB159773